Things have been progressing pretty quickly. Here are some shots of the past weeks progress.

Dug up lot:

Driving pilings:

Slab forms:

In-slab plumbing:

Posted by Sprinky at 07:26 AM | Comments (0)

March 17, 2005

Ground has been broken!

After myriad delays and a thousand days of waiting we finally broke ground on the Loupe compound. I had to look twice to make sure my eyes weren't playing tricks, but there was a small earth moving vehicle parked in the middle of the lot with dirt all around. The stakes were out marking off the perimeter of the structure. It's a great relief to see some actual work being done.